Sarnia advances plans to rebuild 775 metres of Bright’s Grove shoreline

Sarnia is advancing plans to rebuild 775 metres of deteriorating Lake Huron shoreline between Cull Drain and Mike Weir Park. The project follows a 2022 engineering study that estimated the work at $14.6 million and proposed a public waterfront pathway. The new tender moves the project toward detailed design, although construction costs, timing and the pathway’s current status remain unconfirmed.

Sarnia is moving ahead with plans to rebuild 775 metres of deteriorating Lake Huron shoreline in Bright’s Grove, advancing a project first studied four years ago that also envisioned restoring public access along a long-disputed stretch of waterfront.

The City issued an engineering tender on November 10 for shoreline improvements between Cull Drain and Mike Weir Park, where a 2022 engineering study documented failing shoreline protection, erosion and difficulties carrying out repairs along the former Old Lakeshore Road allowance.

The successful engineering firm will develop a comprehensive design for the entire shoreline, with detailed engineering initially focused on the first construction phase. The City anticipates completing the project in at least three phases, depending on available funding.

The new tender represents a progression from preliminary planning toward construction-ready designs.

In 2022, a feasibility study prepared by Shoreplan Engineering Limited identified the corridor as one of Sarnia’s worst-condition shoreline areas. The study examined options for rebuilding deteriorating protective structures, stabilizing the remaining municipal land and reducing erosion risks to neighbouring properties.

Both proposed designs also included a four-metre-wide asphalt pathway, intended to restore public access along the waterfront while providing municipal crews with a route for future shoreline maintenance.

The estimated cost of the combined shoreline reconstruction and pathway was approximately $14.6 million plus HST, including a 35 per cent contingency.

That figure was a preliminary estimate prepared in 2022, not an approved construction budget or a current project price. The new tender concerns engineering services, and an updated total construction cost has not been established in its publicly available description.

The proposed pathway would follow the former Old Lakeshore Road, a public road allowance that has been partly lost to erosion over decades.

Much of the remaining corridor runs behind waterfront homes, where private structures have extended onto portions of the land. Public access has consequently remained restricted along much of the route, despite the City’s position that the property remains a municipal right-of-way.

The ownership question became a significant part of the City’s earlier planning.

Of 18 neighbouring property owners who responded to a municipal survey before the 2022 council decision, 10 agreed the right-of-way belonged to the City, seven disputed municipal ownership and one was uncertain. The City had previously obtained an external legal opinion supporting its position that the corridor remained a public right-of-way.

Council twice voted in 2022 to advance shoreline protection alongside public access.

On May 9, council directed staff to begin preliminary design for shoreline protection and a multi-use pathway. On July 25, it directed staff to include both improvements in future capital budgets, subject to other shoreline protection priorities.

The July motion also addressed encroachments by neighbouring property owners, directing staff to establish temporary agreements until the City was prepared to restore public access. It called for encroachments to be removed where owners refused those agreements.

The shoreline study identified an opportunity to connect existing waterfront routes on either side of the project, potentially creating a longer continuous public pathway along Bright’s Grove’s lakeshore.

The new engineering tender lists the earlier feasibility study among its attachments, although its publicly available description focuses on shoreline protection and does not specify whether the pathway remains part of the current design requirements.

That leaves the precise scope of the proposed public-access improvements unconfirmed.

Engineering firms have until December 3 to submit proposals. The tender does not establish a construction start date or an updated total project cost.

The new tender moves the long-planned shoreline project toward detailed design, with construction expected to proceed in phases as funding becomes available.