Plans to repair Pat Stapleton Arena kept moving into the future. Its failures did not

Sarnia’s capital plans once anticipated major arena work beginning in 2025. By the approved 2026 budget, the entire $10.1-million renewal program was unfunded. Significant water damage has now required another emergency repair.

Pat Stapleton Arena will undergo unbudgeted emergency repairs after deteriorating infrastructure caused significant water damage within community-use areas of the building.

The city says the work is intended to allow the arena to reopen for fall programming, but its July 20 report to council does not identify what failed, which areas were damaged or what the repairs will cost. The expense will be drawn from Sarnia’s Capital Infrastructure account because no funding was previously allocated.

The latest damage comes nearly 16 months after staff warned council that the arena’s major systems and structures were beyond their expected service lives and actively failing.

Approximately $10 million would be required over five years to retain Pat Stapleton as a community ice rink, staff reported in March 2025. Continuing without that investment increased the risk of a catastrophic failure, a long-term unplanned closure and significant emergency costs to reopen the building.

In the approved 2026 budget, none of the resulting $10.1-million renewal program was included in the city’s funded capital plan.

Sarnia has continued to pay for individual projects and emergency replacements intended to keep Pat Stapleton functioning. It has not financed the broader renewal program staff said was necessary to secure the building’s long-term future.

Problems with water entering the arena were documented several years before the latest damage.

A March 2023 building-envelope assessment found recurring leaks along the north side of the arena. Staff reported that a large section of the eavestrough and downspouts had failed, drainage from the roof was inadequate and exterior concrete blocks and grout were deteriorating. Water was affecting the north interior corridor and the Sarnia Legionnaires dressing-room area.

Council redirected $120,000 previously intended for the dressing room and added another $63,010 for exterior repairs after staff concluded that the building envelope had to be addressed before interior renovations proceeded. The city has not said whether the current damage occurred in the same area or resulted from the same deficiencies.

Sarnia’s 2024 budget allocated another $675,000 for Pat Stapleton projects, including an exhaust-fan system, the Legionnaires dressing room, interior renovations and a replacement score clock.

Other failures continued to emerge.

In September 2024, a malfunction involving the electrical panel serving the arena’s chiller units prevented Pat Stapleton from opening for the season as scheduled. The city ordered an emergency panel replacement and electrical repairs that were expected to take several weeks.

In April 2025, both of the arena’s dehumidifiers reached the end of their service lives and could no longer be repaired. The city spent an unbudgeted $162,816 from its building-maintenance operating account to replace them.

Those expenditures addressed specific systems and spaces. They did not fund replacement of the concrete arena floor and chiller plant, roof and exterior walls, heating and ventilation systems, boiler or electrical system identified in the broader building assessment.

Staff’s preliminary estimate placed the floor and chiller work at $3.6 million. Roof and wall replacement was expected to cost between $2 million and $3 million, depending on the material selected. Another $2 million was estimated for heating and ventilation, along with $550,000 for the boiler, $400,000 for roof-access infrastructure and $200,000 for electrical work.

The resulting estimate ranged from $8.75 million to $9.75 million and included contingencies of approximately 40 per cent. It still excluded changerooms, the community room, other public spaces, parking-lot work and required hazardous-material abatement. Staff cautioned that the eventual cost would exceed the preliminary total.

Successive capital plans show the comprehensive work moving further into the future.

Sarnia’s approved 2023 plan anticipated spending $1 million annually on Pat Stapleton beginning in 2025. The approved 2024 plan still showed $800,000 in 2025 and $1 million in 2026.

By the approved 2025 plan, there was no Pat Stapleton allocation in either year. The first amount, $1.5 million, appeared in 2027, with another $8 million spread through 2034.

In the approved 2026 budget, the revised $10.1-million program appeared entirely within the city’s unfunded 10-year capital plan, notionally divided between 2027 and 2030.

Long-term capital plans are forecasts rather than binding promises. Amounts shown in future years still require approval and an available funding source through subsequent budgets.

The progression is nevertheless clear: major reinvestment was initially expected to begin in 2025, was later pushed to 2027 and was eventually categorized as work the city could not finance through its funded capital plan.

Council received the March 2025 condition report and referred the arena’s investment needs to the 2026 budget process.

The city’s budget documents expressly told council members that they could introduce motions to add unfunded projects to the budget. Council approved several amendments during its November deliberations, but the published minutes record no motion to move the Pat Stapleton renewal program into the funded plan.

That does not mean council rejected a fully financed $10.1-million proposal. Staff did not present one with an identified source of money and ask for an up-or-down decision.

The practical result was that the city continued operating Pat Stapleton without financing the comprehensive work staff said was needed to retain it over the long term.

The arena, constructed in 1948, is a single-pad facility with seating for approximately 2,000 people. It hosts more than 70 hours of prime-time ice use each week during its season and serves organizations including the Sarnia Legionnaires, Skate Sarnia, Sarnia Hockey Association, Sarnia Junior Lady Sting, adult recreational leagues and municipal public-skating programs.

Staff warned that an extended closure would not affect only groups normally assigned to Pat Stapleton. Under the city’s ice-allocation policy, users throughout Sarnia’s arena system could be displaced, required to accept non-prime hours or forced to seek ice outside the city.

The city’s approach reflects a broader arena strategy. Staff said available capital was being focused on Progressive Auto Sales Arena and Clearwater Arena, the two year-round twin-pad facilities containing four of Sarnia’s five municipal ice surfaces.

There is a practical rationale for protecting the facilities carrying most of the system’s capacity. But that approach has left the older Brock Street arena dependent on targeted repairs, emergency spending and the continued operation of systems already described as failing.

The latest report warns that additional failures could still cause a long-term unplanned closure, significant emergency expenses and the displacement of youth and adult user groups.

Staff will now prepare options for Pat Stapleton Arena “or alternatives” for consideration during the 2027 budget. The report does not define those alternatives or say whether permanent closure, replacement or construction of ice capacity elsewhere will be considered. No recommendation about the arena’s long-term future has been presented to council.

For several years, Sarnia’s capital plans treated Pat Stapleton as a building that would eventually receive major reinvestment. The 2026 budget instead classified the work as a recognized need for which the city had no funded plan.

The latest damage does not determine whether the arena should be rehabilitated, replaced or closed. It does mean Sarnia is again spending money to keep the building open without having resolved whether it has a long-term future.

That decision has been deferred to the 2027 budget, although the city’s latest report acknowledges that another infrastructure failure could force an extended closure before the arena’s future is resolved.